Milestones

for the planning of the Phase 24 programme
Step  Activity  When 
Evaluation of the needs for new experiments, experiment proposals Until Dec 2017 
Distribution of new experiment proposals not yet included in the programme End of Jan 2018
Deadline for the delivery of draft 5-pager by the PI’s

1 February 2018

Technical Meeting TM-36, Porrentruy

 

TM-36

7/8 Feb 2018 

Porrentruy

Deadline for the delivery of final 5-page documents describing the content and costs of each experiment ("5-pagers") by the PIs

23 Feb 2018

Distribution of the first draft of the programme proposal

9 March 2018

Steering Meeting SM-76 hosted by swisstopo, selection of ongoing and new experiments for Phase 24, extension of rock laboratory

SM-76

22 March 2018,

St-Ursanne

Elaboration of the second draft of the programme proposal for Phase 24, including ongoing and new experiments

Until

mid-April 2017

 
Distribution of the second draft of the programme proposal 21 April 2017
10 

Steering Meeting SM-77, hosted by SCK∙CEN and FANC Brussels/HADES. Agreement on Phase 24 programme, financial contributions of the Partners

SM-77

 16-17 May 2018

Brussels/Mol

 

11 Application to RCJU for authorisation of the Phase 24 programme End of May 2018 
12 Expected autorisations by RCJU  1 July 2018