Milestones

for the planning of the Phase 27 programme
Step  Activity  When 
Evaluation of the needs for new experiments, experiment proposals Until Dec 2020 
Distribution of new experiment proposals not yet included in the programme 31 January 2021
Deadline for the delivery of draft 5-pager by the PI’s

15 February 2021

Distribution of the first draft of the programme proposal

12 May 2021

Steering Meeting SM-85, selection of ongoing and new experiments for Phase 27

SM-85

25 March 2021

Distribution of the first draft of the programme proposal

12 May 2021

Steering Meeting SM-86. Agreement on Phase 27 programme, financial contributions of the Partners

SM-86

2 June 2021

St-Ursanne

Application to RCJU for authorisation of the Phase 27 programme

10 June 2021